Second Deposit LDP

Ended on the 14 April 2023

12. Monitoring and Implementation

Implementation

12.1. In implementing the Revised LDP, the Council will continue to work collaboratively with internal and external partners, organisations and the private sector to implement new development proposals, including employment and housing schemes. The monitoring framework notes the bodies and agencies that are likely to contribute towards delivering specific aspects of the Plan.

12.2. In order to deliver new development the existence of appropriate infrastructure including water supply, sewerage, land drainage, gas, electricity and telecommunications is vital to ensuring the delivery of the Plan's policies and proposals. In some cases, where new or improved infrastructure is required to accommodate new development, this can be provided through scheduled works undertaken by utility companies. Where infrastructure improvements are required to cater for new development but are not programmed to take place within the development's timescale, the prospective developers will need to provide or requisition the infrastructure required to allow development to go ahead.

12.3. The Council will continue to work with DCWW and NRW to ensure that new developments do not place significant pressure on existing infrastructure and do not significantly affect environmental quality. The Council will work in partnership with these agencies and other service providers, utility companies and the private sector, to secure the required infrastructure provision at the optimal time for moving towards achieving the Plan's objectives. This will secure appropriate measures to mitigate the significant adverse effects which new development would have upon the natural environment. SPG and Development Briefs will where necessary provide more detailed information on infrastructure requirements and on working collaboratively to ensure delivery.

12.4. The ability of the public and private sector, to deliver new development and associated infrastructure improvements, will be heavily influenced by external economic circumstances. For this reason, the rate of development over the plan period is likely to vary.

12.5. The Council will also work closely with Local Authorities across the region to ensure alignment between this LDP and their Strategies and in developing regional strategic arrangements, and to ascertain and minimise the likely in-combination effects of this Plan's proposals.

12.6. This chapter takes the strategic policies set out within this Revised LDP and sets out the mechanisms for their implementation. It outlines the partners and agencies, both internal and external, which will contribute towards their implementation, and where appropriate will outline the tools which will be used, such as SPG and Development Briefs.

12.7. The implementation of this Plan will be continually monitored and where appropriate additional mechanisms will be considered to ensure that the best processes are in place, and that the appropriate information is used to inform and guide its implementation.

Monitoring

12.8. This section outlines a monitoring framework which will be used as a tool for measuring the implementation of Revised LDP's policies and proposals. The framework comprises a series of core and local performance indicators intended to monitor the effects and success of the LDP's policies.

(1) 12.9. The information gathered through the monitoring framework will be presented in the Annual Monitoring Report (AMR) which is required to cover the preceding financial year and submitted to the WG by 31st October each year following adoption of the LDP. The AMR is the main mechanism for measuring the implementation and the success of the Plan's policies and will report on issues which impact upon the Plan's objectives. The AMR will also analyse the effectiveness and continued relevance of the Plan's policies in the light of national policy and circumstantial changes. The findings of the AMR could result in amendments to policies in order to improve their effectiveness and in more extreme cases could result in a review of part or of the whole Plan. The report will set out the outcomes of the monitoring framework and the data gathered will, where required, provide a contextual narrative in relation to each finding.

12.10. Irrespective of the AMR's findings, the Council will be required to carry out a review no longer than 4 years from the date of adoption. This could result in the production of a replacement/revised Plan or in the alterations of aspects of the Plan.

12.11. LDP Regulations prescribes the following indicator required by legislation which must be included in the AMR:

  • The number of net additional affordable and general market dwellings built in the LPA's area.

12.12. Table 29 of the Development Plans Manual Edition 3 sets out additional key indicators applicable to the Plan.

12.13. These indicators required by WG are identified in the monitoring framework. Contextual indicators will also be used in the AMR to evaluate if it is the Plan which is not achieving the targets or if there are external factors (e.g. the economy or changes in funding sources ) which are outside of the planning system's control which influence the outcomes of the framework.

12.14. As reflected within the ISA, the SEA Regulations (Article 17) require that the significant environmental effects of the Plan be monitored so that any unforeseen adverse effects can be remediated. To avoid duplication between the monitoring carried out for the ISA (incorporating the SA/SEA) and the rLDP, some indicators have been combined for the two processes to aid clarity. This is demonstrated within Chapter 8 of the ISA report.

12.15. The following options are available to the Council in association with each of the indicators and their triggers. The AMR will assess the severity of the situation associated with each indicator and recommend an appropriate response.

Table 12: Monitoring Outcomes

Continue Monitoring (Green)

Where indicators are suggesting that LDP policies are being implemented effectively and there is no cause for a review.

Officer / Member Training Required (Blue)

Where indicators associated with planning applications suggest that policies are not being implemented as they were intended, and further officer or Member training is required.

Supplementary Planning Guidance (SPG) / Development Briefs Required (Purple)

Whilst the Council will be preparing SPG and Development Briefs throughout the Plan period, indicators may suggest that further guidance should be provided to developers on how a policy should be properly interpreted. Additionally, should sites not be coming forward as envisaged, the Council will actively engage with developers / landowners to bring forward Development Briefs on key sites to help commence the development process.

Policy Research / Investigation (Yellow)

Where monitoring indicators suggest the LDP policies are not being as effective as intended, further research and investigation, including the use of contextual indictors (as outlined above) and comparisons with other local authorities and national statistics where appropriate will be undertaken to inform any decision to formally review the policy.

Review Policy (Orange)

Where monitoring indicators suggest that amendments to the LDP would be beneficial, the Council will consider modifying the Plan as appropriate. This may result in a review of Plan policies.

Plan Review (Red)

Where the monitoring indicators suggest the Plan and its strategy is not being implemented. An investigation into the reasons behind it not being implemented may result in a formal review of the Plan.

LDP and ISA Objectives

Policy

Indicator Ref:

Monitoring Indicator

Target

Trigger Point

Source

Strategic Policy - SP1: Strategic Growth

SO3, SO10

ISA1, ISA10, ISA15

SP1

SP4

HOM1 HOM2 HOM3

MI. 1

Indicator Required by Legislation:

Number of net additional open market dwellings and affordable homes built in the Plan area.

To deliver 8,822 dwellings in total during the Plan period - based on an annual completion rate of 588 units and 126 affordable units per year.

Delivery of below the Plan's annual build rate / target for at least two consecutive years.

Carmarthenshire County Council

SO3, SO12

ISA10, ISA14

SP1

MI. 2

Local Indicator:

Job creation.

Monitored for information purposes.

No target.

No trigger.

Carmarthenshire County Council

SO1, SO2, SO3, SO13

ISA1, ISA2, ISA12, ISA14

SP1

SG3

MI. 3

Local Indicator:

Production of SPG on The Pembrey Peninsula.

Adopt SPG by December 2025.

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

Strategic Policy – SP 2: Retail and Town Centres

SO4

ISA1, ISA6, ISA14

SP2

MI. 4

Local Indicator: Vacant Retail Units of commercial properties

Vacancy rates of commercial properties within defined town centre boundary.

Vacancy levels increase

Retail and Town Centre Audit

Strategic Policy – SP 3: Sustainable Distribution – Settlement Framework

SO6, SO10

ISA1, ISA10

SP3

SP4

MI. 5

Key Indicator:

Proportion of housing permitted on allocations per tier of the settlement hierarchy

The distribution of dwellings to be in accordance with the proportions specified in the Plan

Deviation of +/- 10% from the expected distribution of allocations within the tiers for at least two consecutive years

Carmarthenshire County Council

Strategic Policy – SP 4: A Sustainable Approach to Providing New Homes

SO10

ISA10, ISA15

SP1

SP4

HOM1

MI. 6

Key Indicator:

The level of housing completions (private and affordable) monitored against the Anticipated Annual Build Rate (AABR).

.

Annual completions as per the housing trajectory.

Annual completion levels falling below the levels set out in the housing trajectory for at least two consecutive years.

SO10

ISA10, ISA15

SP1

SP4

HOM1

MI. 7

Key Indicator:

Total cumulative completions monitored against the anticipated cumulative completion rate.

Cumulative completions as per housing trajectory.

Cumulative completion levels falling below the levels set out in the housing trajectory for at least two consecutive years.

Carmarthenshire County Council

SO6, SO10

ISA10, ISA15

SP4

HOM1

MI. 8

Local Indicator:

Number of dwellings delivered on Housing Allocations.

To deliver 6,824 dwellings on allocated sites.

The overall number of new housing units built on allocated sites which fall below the annual requirement for 2 consecutive years

Carmarthenshire County Council

SO6, SO10

ISA10, ISA15

SP4

HOM2

MI. 9

Local Indicator:

Small Sites (less than 5 units) Allowance – Number of dwellings delivered in tiers 1 - 3.

To meet the planned target of 1,575 dwellings on small sites

20% of +/- 105 dwellings permitted annually on small sites in tiers 1 - 3.

Carmarthenshire County Council

SO10

ISA10, ISA15

SP4

MI. 10

Local Indicator:

Windfall Allowance – number of dwellings delivered on windfall sites (excluding small sites allowance).

To meet the planned target of 1,305 dwellings on large windfall sites.

20% +/- 87 dwellings permitted annually on windfall sites (+5 no.).

Carmarthenshire County Council

SO10

ISA1, ISA10, ISA11, ISA15

SP4

HOM3

MI. 11

Local Indicator:

Net increase in number of new homes in Rural Villages (Tier 4).

The number of open market homes within each Rural Village should not exceed the 10% cap above the number of existing homes in the settlement, as at the LDP base date

The net increase of open market homes within a Rural Village exceeds the 10% cap above the number of existing homes in the settlement, as at the LDP base date.

Carmarthenshire County Council

SO10

ISA1, ISA10, ISA11, ISA15

SP4

HOM3

MI. 12

Local Indicator:

Production of SPG on Homes in Rural Villages

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Strategic Policy – SP 5: Affordable Homes Strategy

SO10

ISA6, ISA10, ISA12, ISA15

SP5

HOM4 AHOM1 AHOM2

MI. 13

Key Indicator:

The level of affordable housing completions monitored against the plan's overarching target.

To deliver 1900 affordable homes in total by 2033.

To deliver 126 affordable home annually.

Delivery falls below the Plan's annual build rate / target for at least two consecutive years

Carmarthenshire County Council

SO10

ISA6, ISA10, ISA12, ISA15

SP5

HOM4 AHOM1 AHOM2

MI. 14

Key Indicator:

Tenure of affordable housing completions.

Tenure split (social rented and intermediate) in line with need identified in the Local Housing Market Assessment (LHMA).

Non delivery of the identified tenure split over at least 2 consecutive years.

Carmarthenshire County Council

SO10

ISA6, ISA10, ISA12, ISA15

SP5

AHOM1 AHOM2

MI. 15

Key Indicator:

Trends in key determinants of market conditions and viability such as, house prices, land values, build costs.

Policy requirements are reflective of the current economic circumstances and financial viability.

Average house prices increase or decrease by 5% above the base levels sustained over 1 year.

Council Valuers

SO10

ISA10, ISA12, ISA15

SP5

AHOM1

HOM1

MI. 16

Key Indicator:

Delivery of the affordable housing policy - thresholds and percentage targets for each housing allocation site with a permission.

The proportion of affordable dwellings permitted on residential allocations should be in accordance with Policy AHOM1.

The proportion of affordable dwellings permitted on residential allocations not in accordance with HOM1.

Carmarthenshire County Council.

SO10

ISA6, ISA10, ISA12, ISA15

SP4

AHOM1 AHOM2

MI. 17

Local Indicator:

Production of SPG on Affordable Housing.

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Strategic Policy – SP 6: Strategic Sites

SO3, SO12

ISA12, ISA13, ISA14

SP4

SP6

SP7

MI. 18

Key Indicator:

Pentre Awel – Delivery of housing element of the site.

Delivery of the non-residential component of the site.

Annual completions as per the housing trajectory.

Granting of permission for the non-housing component site during the Plan period

Annual completion levels falling below the levels set out in the housing trajectory.

Permission for the non-residential component not secured prior to the first review of the Plan.

Carmarthenshire County Council

City Deal

SO3, SO12

ISA11, ISA12, ISA13, ISA14

SP6

SP7

MI. 19

Key Indicator:

Delivery of Yr Egin development.

Granting of permission for the site during the Plan period.

Permission not secured prior to the first review of the Plan.

Carmarthenshire County Council

City Deal

Strategic Policy – SP 7: Employment and the Economy

SO3, SO12

ISA10, ISA14

SP1

SP6

SP7

SG1

MI. 20

Key Indicator:

Employment land take-up against employment allocations.

Employment land permitted (ha) on allocated employment sites.

No permissions on employment land allocations for at least two consecutive years

Carmarthenshire County Council

SO3, SO12

ISA10, ISA13, ISA14

SP1

SP6

SP7

SG1

MI. 21

Key Indicator:

Job growth

Use Class B job growth in line with the strategy.

No permission for developments that create Use Class B jobs in a year.

Carmarthenshire County Council

SO3, SO12

ISA10, ISA14

EME1

MI. 22

Local Indicator:

Employment land lost to other land uses (includes identified existing and/or proposed employment sites)

No loss to other uses unless it can be justified through LDP policy.

Permission granted for non-employment uses not in accordance with LDP policy

Carmarthenshire County Council

SO3, SO12

ISA14

EME4

MI. 23

Local Indicator:

Planning permissions for employment uses outside of identified existing or proposed employment sites where they are contrary to the provisions of Policy EME4

Ensure that employment uses outside of proposed and/or identified existing employment sites are in accordance with Policy EME4

Planning permission for employment uses on land outside of proposed and/or identified existing employment sites where they are contrary to Policy EME4

Carmarthenshire County Council

Strategic Policy – SP 8: Welsh Language and Culture

SO11

ISA1, ISA11

SP8

WL1

MI. 24

Local Indicator:

Production of SPG on Welsh Language and New Developments.

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO11

ISA11

SP8

WL1

MI. 25

Local Indicator:

Planning applications supported by Welsh Language Action Plans or Welsh Language Impact Assessments

Planning Applications to be supported by relevant documentation in accordance with Policy WL1

Planning applications not supported by relevant documentation in accordance with Policy WL1

Carmarthenshire County Council

SO11

ISA11, ISA15

SP8

WL1

MI. 26

Local Indicator:

Welsh speaking % in the County

Increase the proportion of Welsh speakers in the County

No trigger. Monitoring for contextual information.

Carmarthenshire County Council

Census

Office of National Statistics

Welsh Government Data

Strategic Policy – SP 9: Infrastructure

SO1, SO2, SO14

ISA1, ISA2, ISA5

SP9

INF4

MI. 27

Key Indicator:

The delivery of key infrastructure that underpins the plan strategy.

Monitor the development of new infrastructure, such as road and rail improvements, utility, and biodiversity enhancements.

No trigger. Monitoring for contextual information. Reference to other indicators within this framework.

Carmarthenshire County Council

SO1, SO14

ISA1, ISA2, ISA5

SP9

INF4

MI. 28

Local Indicator:

Production of SPG on The Burry Inlet.

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO14

ISA1

SP7

INF1

MI. 29

Local Indicator:

Production of SPG on Planning Obligations.

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO2, SO14

ISA1, ISA12

SP7

INF2

MI. 30

Local Indicator:

Production of SPG on Health Impact Assessments

Adopt SPG by Summer 2025

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

Strategic Policy – SP 10: Gypsy and Traveller Provision

SO10

ISA10, ISA15

SP10

GTP1

MI. 31

Key Indicator:

Gypsy and Traveller sites / pitches built on allocated sites.

To provide the required pitches identified within the GTAA. to be met in accordance with identified need.

No planning permission secured on an allocated site.

Carmarthenshire County Council

SO10

ISA10, ISA15

SP10

GTP1

MI. 32

Local Indicator:

Gypsy and Traveller sites / pitches built on unallocated sites

No target

The granting of any planning permission and/or traveller site.

Carmarthenshire County Council

SO10

ISA10, ISA15

SP10

GTP1

MI. 33

Local Indicator:

The need for Gypsy and Traveller transit sites

No unauthorised Gypsy and Traveller site recorded in one settlement for 3 consecutive years

1 unauthorised Gypsy and Traveller site recorded in one settlement for 3 consecutive years

Carmarthenshire County Council

Strategic Policy – SP 11: The Visitor Economy

SO13

ISA1, ISA14

SP11

VE1

VE2

VE3

VE4

MI. 34

Local Indicator:

Total economic impact of tourism in Carmarthenshire

No target

No trigger. Monitoring for contextual information

STEAM Report prepared by GTS UK (Carmarthenshire CC Marketing and Media Annual Report)

SO13

ISA1, ISA14

SP11

VE1

VE2

VE3

VE4

MI. 35

Local Indicator: Production of SPG on Alternative Luxury Camping

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set

Strategic Policy – SP 12: Placemaking and Sustainable Places

SO9

ISA1, ISA8, ISA9, ISA12, ISA15

SP12

MI. 36

Local Indicator:

Production of SPG on Placemaking and Sustainable Places

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set

SO9, SO11

ISA1, ISA11

SP12

PSD9

MI. 37

Local Indicator:

Production of SPG on advertisements (guidance on bilingual requirements)

Adopt SPG by Summer 2025

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO1, SO2, SO7, SO9

ISA1, ISA2, ISA3, ISA4, ISA5, ISA6, ISA7, ISA8, ISA9, ISA12, ISA15

SP12

PSD3 PSD4

MI. 38

Local Indicator:

The provision of Green and Blue Infrastructure in the County.

No target

No trigger. Monitor for information purposes.

Carmarthenshire County Council

ISA1, ISA2, ISA3, ISA4, ISA5, ISA6, ISA7, ISA8, ISA9, ISA12, ISA15

SP12

PSD3 PSD4

MI. 39

Local Indicator: Production of SPG on Green and Blue Infrastructure Networks and Development

Adopt SPG by Summer 2025

Failure to progress in accordance with the timetable set

SO2, SO4

ISA1, ISA9, ISA12, ISA15

SP12

PSD7

MI. 40

Local Indicator:

The amount of identified open space lost to development

No identified open space should be lost to development except where in accordance with Policy PSD7

Identified open space is lost contrary to the provisions of Policy PSD7

SO1

SP12

PSD12

MI. 41

Local Indicator: Production of SPG on Light Pollution

Adopt by December 2025

Failure to progress in accordance with the timetable set

Strategic Policy – SP 13: Rural Development

SO5

ISA1, ISA8

SP13

RD4

MI. 42

Local Indicator:

Production of SPG on Conversion and reuse of rural buildings for residential use

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set

Strategic Policy – SP 14: Maintaining and Enhancing the Natural Environment

SO1, SO9

ISA1, ISA2

SP14

NE4

MI. 43

Local Indicator:

Continue to work towards securing a minimum of 100 ha of suitable habitat for the Marsh Fritillary Butterfly within the Caeau Mynydd Mawr SPG project

Increase in every AMR period in the area of managed habitat in suitable condition

No increase in the area of managed habitat in suitable condition for 4 consecutive AMR periods.

Caeau Mynydd Mawr Project Steering Group.

Carmarthenshire County Council – Performance Improvement Management System (PIMS).

SO1, SO9

ISA1, ISA2

SP14

NE4

MI. 44

Local Indicator:

Production of SPG on Caeau Mynydd Mawr.

Adopt SPG by October / November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO1, SO9

ISA1, ISA2, ISA9

SP14

PSD4

MI. 45

Local Indicator:

Production of SPG on Trees and planting as part of new developments

Adopt SPG by Summer 2025.

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO1, SO9

ISA1, ISA2

SP14

NE1

MI. 464

Local Indicator:

Production of SPG on Sites of Importance for Nature Conservation Value (SINCs).

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO1, SO9

ISA1, ISA2

SP14

NE2

MI. 47

Local Indicator:

Production of SPG on Nature Conservation and Biodiversity

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO1, SO9

ISA1, ISA2

SP14

BHE2

MI. 48

Local Indicator:

Production of SPG on Landscape Character.

Adopt SPG by Summer 2025.

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

Strategic Policy – SP 15: Protection and Enhancement of the Built and Historic Environment

SO5

ISA1, ISA8

SP15

MI. 49

Local Indicator:

Production of SPG on Archaeology

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

SO5

ISA1, ISA8

SP15

MI. 50

Local Indicator:

Production of SPG on the Built and Historic Environment

Adopt SPG by December 2025

Failure to progress in accordance with the timetable set.

Carmarthenshire County Council

Strategic Policy – SP 16: Climate Change

SO7

ISA1, ISA4

SP16

CCH5

MI. 51

Key Indicator:

Amount of highly vulnerable development (by TAN15 paragraph 5.1 development category) permitted in C2 flood risk zones not meeting all TAN15 tests (paragraph 6.2 i-v).

No applications permitted for highly vulnerable development in C1 and C2 flood risk zone contrary to NRW advice.

1 application permitted for highly vulnerable development in C2 flood risk zone contrary to NRW advice.

Carmarthenshire County Council

SO7

ISA1, ISA4

SP16

CCH1

MI. 52

Local Indicator:

Production of SPG on Renewable Energy.

Adopt SPG by December 2025

Failure to progress in accordance with the timetable set.

SO7

ISA1, ISA4

SP16

CCH1

MI. 53

Local Indicator:

To increase the amount of energy and heat produced in the County from renewable sources

Annual increase in the permitted capacity of renewable energy and heat permitted.

No planning applications permitted for renewable energy in one year.

Carmarthenshire County Council

SO1

ISA1, ISA2, ISA5, ISA7

SP16

MI. 54

Local Indicator: Production of SPG on Water Quality – Protected Riverine SACs

Adopt SPG by October/November 2024

Failure to progress in accordance with the timetable set.

SO7, SO8

ISA1, ISA4, ISA14

SP16

CCH3

MI. 55

Local Indicator: Produce SPG on Electric and Ultra Low Emission Vehicles in Developments

Adopt SPG by Summer 2025

Failure to progress in accordance with the timetable set.

Strategic Policy – SP 17: Transport and Accessibility

SO8

ISA6

TRA1

MI. 56

Local Indicator: Progress toward the implementation of identified road scheme

Implementation in accordance with the delivery timetables

The road scheme identified is not delivered in accordance with delivery timetables

Local Highway Authority

SO7, SO8

ISA4, ISA6, ISA12, ISA15

SP17

TRA2

MI. 57

Local Indicator: Amount of walking and cycling infrastructure granted planning permission.

Increase in the number of schemes permitted.

No trigger. Monitoring for contextual information

Local Highway Authority

Local Planning Authority

SO8

ISA6

TRA1

MI. 58

Local Indicator: Implementation of Welsh Government Road Schemes – including Llandeilo Bypass

Monitored for information purposes

No target

No trigger. Monitoring for contextual information

Welsh Government

Strategic Policy – SP 18: Mineral Resources

SO7

ISA6

SP18

MR1

MI. 59

Local Indicator:

The amount of hard rock landbank

Maintain a minimum aggregate landbank of 10 years for hard rock

Less than 10 years hard rock landbank.

Operators

Planning Policy and guidance

LDP policies

Development management and decision-making process.

SO7

ISA6

SP18

MR1

MI. 60

Local Indicator:

The amount of sand and gravel landbank

Maintain a minimum landbank for sand and gravel of 7 years.

Less than 7 years sand and gravel landbank.

Operators

Planning Policy and guidance

LDP policies

Development management and decision-making process.

SO7

ISA6

MR2

MI. 61

Local Indicator:

Sterilising developments permitted within mineral buffer zones.

No permanent, sterilising development within a mineral buffer zone.

5 permanent, sterilising developments permitted within a mineral buffer zone contrary to Policy over 3 consecutive years.

Planning Policy and guidance

LDP policies

Development management and decision-making process.

SO7

ISA6

MR3

MI. 62

Local Indicator:

Sterilising developments permitted within a mineral safeguarding areas.

No permanent, sterilising development will be permitted within a mineral safeguarding area.

5 permanent, sterilising developments permitted within a mineral safeguarding area over 3 consecutive years.

Planning Policy and guidance

LDP policies

Development management and decision-making process.

Strategic Policy – SP 19: Waste Management

SO7

ISA6

SP19

MI. 63

Local Indicator:

Monitor planning permissions for waste management facilities

Maintain sufficient capacity to meet local need

Information set out within the Annual Mid and South West Wales Waste Planning Monitoring Reports

Planning Policy and guidance

LDP policies

Development management and decision-making process

For instructions on how to use the system and make comments, please see our help guide.
back to top back to top