Cefnogi

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5734

Derbyniwyd: 25/05/2023

Respondent ID: 3253

Ymatebydd: Natural Resources Wales

Crynodeb o'r Gynrychiolaeth:

INF4: Llanelli Waste Water Treatment Surface Water Disposal
We support the inclusion of this policy and the supporting Burry Inlet SPG. As you know there has been a long-established partnership approach to dealing with concerns on the risk of deterioration of water quality on the Carmarthen Bay and Estuaries European Marine Site.
Paragraph 11.203 states that Dwr Cymru Welsh Water (DCWW) have confirmed that there is sufficient capacity within Llanelli Waste Water Treatment Works to deliver the Plan’s identified growth without breaching their permit requirements.
We acknowledge that in addition to the implementation of the requirements of the Memorandum of Understanding on new developments, several improvement schemes have also been undertaken within the catchment since it was introduced.
We are satisfied that if DCWW have confirmed the above in writing, the Policy, with its requirements for surface water removal by the major developments, should ensure that the identified growth will cause no detriment to water quality from the generation of foul flows.

Atodiadau:


Ein hymateb:

Support welcomed