An objection is made to the allocation for residential development at Land off Parc y Delyn (LDP Ref. No. PrC1/h4). It is considered that its continued inclusion will lead to the Plan failing the 3 Tests of Soundness.
An adoptable road to serve the site would be impossible, which in itself would question its deliverability.
Remove site from the Plan
Further to the publication of the above document, we have been asked by our Clients to review
its contents, policies and proposals and advise them of any aspects we believe would
unreasonably affect their aspirations and interests. In doing so we consider it necessary to
make a formal representation to the “soundness” of the Carmarthenshire Deposit Local
Development Plan in relation to the allocation for residential development at Land off Parc y
Delyn (LDP Ref. No. PrC1/h4) under the provisions of Policy HOM1. The proposed allocation
has been fully assessed and in considering its context and background (summarised below) it is
considered that its continued inclusion will lead to the Plan failing the 3 Tests of Soundness for
the reasons set out below.
Site Background and Context
The allocation relates to the land shaded brown on the Proposals Map extract below and is
proposed for allocation in the 2nd Deposit LDP for the purposes of 17 residential units.
Plan A
(Extract of Proposals Map for Carmarthen and Land off Parc y Delyn Allocation)
As part of the current consultation process into the 2nd Deposit LDP, the Council have again published a “Site Assessment Table” (2023), which provides details of the Council’s analysis of each received Candidate Site submission and existing allocations within the current adopted LDP. Proposed allocation PrC1/h4 was considered as part of this process and as a result the Council concluded as follows:
“Site to be allocated with reference PrC1/h4.”
It is clear from the above that the Council considers that the site is deliverable for the purposes of 17 houses, although it is not clear on what basis this conclusion has been made.
The allocation is greenfield in nature with its topography sloping gradually from north to south. The eastern perimeter of the allocation is bordered by the Parc y Delyn residential estate while the remaining borders adjoin further greenfield land as can be seen from the aerial photograph below (outlined in red below).
Photograph 1
(Extract from Google Earth – June 2021)
Pedestrian access to the allocation is currently gained via Parc y Delyn, that being off Penlan Road (see below).
Photograph 2
(Streetscene of Access to Allocation Site)
There are also 2 trees located at the acces to the site that have Tree Protection Orders (TPO) placed upon them with reference W13 as can be seen in Photograph 3 below. This would therefore indicate that an adoptable road to the serve the Allocation would be impossible, which in itself would question its deliverability.
Photograph 3
(Map Showing TPO’s in area)
Tests of Soundness
Based on the above information and the guidance documents provided by the Welsh Government and Council itself, it is considered that the inclusion of the adoption of the LDP in its current form with the inclusion of the allocation in question, would result in it failing to meet the requirements of the Tests of Soundness, for the reasons summarised below.
Test 1 – Does the Plan Fit?
The allocation fails the test of soundness as its inability to be delivered is in conflict with Paragraph 4.2.2 of Planning Policy Wales (Edition 11) requirements of national planning policy.
Test 2 – Is the Plan appropriate?
The allocation fails the test of soundness as its inability to be delivered would fail to address key issues set out by the Plan (housing supply). The Council’s decision to allocate the land appears to not have been done so on credible or robust evidence.
Test 3 – Will the Plan deliver?
The allocation fails to test the soundness as the site is clearly unable to deliver any new housing. Given the important biodiversity features of the site and the two TPO’s at the sites
access point meaning that the site would not accessible by vehicles, the allocation in question would not be fit, nor sustainable for residential allocation.
In summary, we object to the inclusion of the allocation in question on the basis of the above and that its inclusion within the Plan would result in the document being ‘unsound’.
We therefore respectfully request that this Representation be given careful examination, and that the allocation be removed to ensure that the document passes all the relevant tests of soundness.
Disagree, the allocation of the site within the LDP for residential purposes has been subject to full consideration through the site assessment methodology. As part of this assessment process a detailed site pro forma has been prepared.