Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
Chwilio sylwadau
Canlyniadau chwilio Welsh Government
Chwilio o’r newyddSylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/004/032
ID sylw: 1967
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Site can only come forward with delivery of Ammanford distribution road. Fully evidenced prior to inclusion. This is the same for all adjoining potential site allocations. Significant cumulative impacts that are required to be modelled/mitigated prior to LDP2 inclusion.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/159/014
ID sylw: 1968
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Site can only come forward with delivery of Ammanford distribution road. Fully evidenced prior to inclusion. This is the same for all adjoining potential site allocations. Significant cumulative impacts that are required to be modelled/mitigated prior to LDP2 inclusion.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/159/005
ID sylw: 1969
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Site can only come forward with delivery of Ammanford distribution road. Fully evidenced prior to inclusion. This is the same for all adjoining potential site allocations. Significant cumulative impacts that are required to be modelled/mitigated prior to LDP2 inclusion.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/159/007
ID sylw: 1970
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Site can only come forward with delivery of Ammanford distribution road. Fully evidenced prior to inclusion. This is the same for all adjoining potential site allocations. Significant cumulative impacts that are required to be modelled/mitigated prior to LDP2 inclusion.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
Rhydaman
ID sylw: 1971
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Sites northwest of Ammanford - potential cumulative impacts - need TS.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/004/012
ID sylw: 1972
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Constraints at trunk road junction - needs to be evidenced before inclusion. TA.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/004/033
ID sylw: 1973
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Potential cumulative constraints in line with other development west of the trunk road development. TA required.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/004/023
ID sylw: 1974
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Potential cumulative constraints in line with other development west of the trunk road development. TA required.
All other development north west of the trunk road junction have capability to have cumulative significant impacts. Will all require evidencing for cumulative impacts at the trunk road junction.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/004/003
ID sylw: 1975
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Subject to Transport Statement.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.
Sylw
Safleoedd Ymgeisio a Gyflwynwyd / Candidate Site Submissions
SR/082/010
ID sylw: 1976
Derbyniwyd: 08/02/2019
Ymatebydd: Welsh Government
Significant development site with insufficient width to provide access to DMRB standards.
The respondent has compiled some general comments from Welsh Government Network Management Division as highway authority for the trunk road and motorways in Wales and also makes a number of site specific comments. The respondent states that the strategic trunk road network is for the safe and expeditious movement of long distance traffic. In order to maintain free-flow and safety, there is a general presumption against new access onto trunk roads. Further detailed advice is given on how developments should seek to access trunk roads, with reference made to guidance and legislation (including the Design Manual for Roads and Bridges (DMRB) and the Active Travel Act).
In order for the trunk road highway authority to be in a position to make a considered view, the onus is on the forward planning authority to provide highway evidence in both capacity and safety terms. This will scope the consideration of existing network capacity constraints, agreed infrastructure upgrades and outline delivery streams (such as planning obligations).
Advice is provided on the potential accompanying evidence required with an application (eg Transport Statement (TS) or Transport Assessment (TA)) - commensurate with the scale of the proposal. Applications are judged on their individual merits and specific supporting traffic impact detail may be requested in order to consider network impacts. Where designs are not DMRB compliant there is a right to issue a direction to refuse an application.
Where developments require improvements to existing or new connections to the trunk road and these are agreed at planning, the developer will be required to enter into an appropriate legal agreement for their delivery, generally via Section 184 and Section 278 of the Highways Act.