PrC3/MU1

Yn dangos sylwadau a ffurflenni 1 i 1 o 1

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 4930

Derbyniwyd: 13/04/2023

Respondent ID: 5620

Ymatebydd: Parc Emlyn Developments Limited

Asiant : Lightwater TPC (Adrian Thompson)

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

See statement by Lightwater TPC (13 April 2023). In summary, the Deposit Plan as currently set out does not meet the second test of soundness. It is not appropriate because
• the rationale behind the plan’s policy has not been demonstrated
• real alternatives have not been properly considered, and
• it is not logical and reasonable.


Ein hymateb:

Disagree, the allocation of the site within the LDP for residential purposes has been subject to full consideration through the site assessment methodology. As part of this assessment process a detailed site pro forma has been prepared.