PrC2/h10

Yn dangos sylwadau a ffurflenni 1 i 3 o 3

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5380

Derbyniwyd: 14/04/2023

Respondent ID: 4879

Ymatebydd: Barratt David Wilson Homes

Asiant : Boyer Planning

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

BDW objects to the proposed allocation of this site. We have serious concerns regarding its deliverability. The site is a former quarry and is covered by dense vegetation with complicated access arrangements which are affected by Flood Risk Zone C2 constraints. It has not been demonstrated that this site can be accessed without unacceptable flood risk consequences. The site is also
brownfield in nature, and it should be demonstrated that appropriate ground investigation work has been undertaken to demonstrate that the site is viable and deliverable. The site should be removed as a draft allocation from the Deposit Revised LDP.

Atodiadau:


Ein hymateb:

The allocation of the site within the LDP for residential purposes has been subject to full consideration through the site assessment methodology. As part of this assessment process a detailed site pro forma has been prepared.

A response has been received from NRW relating to important ecological connectivity. Further evidential work will be required for examination, with the matter to be considered further at examination

Cefnogi

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5638

Derbyniwyd: 23/05/2023

Respondent ID: 5826

Ymatebydd: Dwr Cymru/Welsh Water

Crynodeb o'r Gynrychiolaeth:

Water Supply and Public Sewerage
No issues

WwTW:
Llanelli – no issues

Atodiadau:


Ein hymateb:

Information welcomed

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5726

Derbyniwyd: 25/05/2023

Respondent ID: 3253

Ymatebydd: Natural Resources Wales

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Heb nodi

Crynodeb o'r Gynrychiolaeth:

Site appears to provide important ecological connectivity features. Loss of ecosystem connectivity would be at odds with the fundamental aims of maintaining and enhancing biodiversity and your Authority’s duty under Section 6, Part 1 of the Environment (Wales) Act 2016. The Well-Being of Future Generations (Wales) Act and the Environment (Wales) Act provide a duty to maintain
and enhance the resilience of ecosystems.

- PrC2/h10 The Dell, Furnace, Llanelli
Following discussions on this allocation it was confirmed that the surrounding woodland will be retained to maintain a green corridor providing connectivity with the main woodland and the Dell. The mitigation required may reduce the amount of land available for development and the site would need to be allocated on this principle to ensure the soundness of the plan.

Atodiadau:


Ein hymateb:

The allocation of the site within the LDP for residential purposes has been subject to full consideration through the site assessment methodology. As part of this assessment process a detailed site pro forma has been prepared.

Further evidential work will be required for examination, with the matter to be considered at examination