CCH4: Ansawdd Dŵr a Diogelu Adnoddau Dŵr

Yn dangos sylwadau a ffurflenni 1 i 4 o 4

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 4771

Derbyniwyd: 11/04/2023

Respondent ID: 2558

Ymatebydd: The Home Builders Federation

Cydymffurfio â’r gyfraith? Ydi

Cadarn? Ydi

Crynodeb o'r Gynrychiolaeth:

The reference to SuDS in the policy wording is not necessary as it is required by separate legislation. It can if required be referred to in the supporting text.

The final paragraph relating to Phosphates needs to be reworded as mitigation will not be required in all cases due to the approach taken by NRW following the ongoing permit reviews.


Ein hymateb:

Disagree. PPW makes reference to SuDS and it it’s importance in being integral to the design of new development.
In respect of the second part of the objection, it is considered that the wording of the Policy is appropriate and more guidance will provided in Supplementary Planning Guidance.

Cefnogi

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5566

Derbyniwyd: 12/04/2023

Respondent ID: 5816

Ymatebydd: Welsh Government

Crynodeb o'r Gynrychiolaeth:

Phosphates
In January 2021, Natural Resources Wales (NRW) published evidence that showed over 60% of riverine Special Areas of Conservation (SAC) waterbodies failed against phosphorus standards. As a result of these failings, NRW issued planning advice to avoid further deterioration in environmental capacity where new developments have the potential to affect phosphorus sensitive riverine SACs and achieve ‘nutrient neutrality’.
The advice from NRW relates to riverine SACs whose drainage catchments extend into Carmarthenshire, namely the Afon Teifi, Afon Tywi, Afon Cleddau, River Wye and River Usk. Of these five waterbodies, only two are affected by the proposed housing allocations in the plan draining to either the Afon Teifi or Afon Tywi.
The Council has sought to reduce the number of housing allocations in the Afon Tywi to six sites (102 units) and fifteen sites (189 units) in the Afon Teifi. The impact of these reductions has reduced phosphorous levels by 43% and 49% respectively in each of the waterbodies. This reduction, coupled with amendments to Policy CCH4 and the availability of land for potential wetland creation to promote the natural uptake of phosphates in Carmarthenshire, have all been screened as part of the Councils Habitats Regulations Assessment (February 2023) and concluded that the plan will have no adverse effect on the integrity of European sites. The delivery of allocated sites and implementation of long-term mitigation measures is for the statutory bodies of NRW and Welsh Water (WW) to comment in more detail.
(Category C)

Atodiadau:


Ein hymateb:

Comments noted

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5760

Derbyniwyd: 25/05/2023

Respondent ID: 3253

Ymatebydd: Natural Resources Wales

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Heb nodi

Crynodeb o'r Gynrychiolaeth:

We note paragraph 4.2.10 of the HRA Addendum Report advises that policy CCH4:
Water Quality and Protection of Water Resources is ‘…further revised to be inclusive of all pathways (e.g., wastewater and diffuse run-off)’. However, no change has been made to the policy and there is no explanation given for this. To ensure that the policy meets the tests of soundness we advise further clarity is provided on this point.

Atodiadau:


Ein hymateb:

Changes to the policy will be discussed at examination.

Gwrthwynebu

Ail Gynllun Datblygu Lleol Adneuo Diwygiedig Sir Gaerfyrddin

ID sylw: 5822

Derbyniwyd: 14/04/2023

Respondent ID: 3885

Ymatebydd: Ffos Las Ltd

Asiant : Carney Sweeney

Cydymffurfio â’r gyfraith? Heb nodi

Cadarn? Nac Ydi

Crynodeb o'r Gynrychiolaeth:

Based on current draft allocations the riverine SAC phosphate constraint will likely significantly constrain the delivery of housing across the County over the emerging plan period, particularly in Pencader and Llandovery. The Council’s previous conclusions on need should be thoroughly reassessed. The proposed site at land adjacent to Culla Road Roundabout (ref: SR/023/003)
is unconstrained and immediately deliverable.

Atodiadau:


Ein hymateb:

Disagree. The strategy of the revised LDP seeks to support the distribution of housing and economic growth which is of a scale and nature appropriate to its cluster and has taken into account SAC riverine phosphate constraints. In this respect the revised LDP seeks to ensure that development is appropriate to the settlement and reflective of its ability to accommodate growth and the services and facilities available.