Matters Arising Changes 2026
ID sylw: 5994
Derbyniwyd: 25/06/2026
Respondent ID: 2320
Ymatebydd: Dwr Cymru/Welsh Water
MAC 125 Appendix 9
We note that a new appendix is included to provide site information for the regeneration and mixed-use sites, including the infrastructure requirements. DCWW has made representations at the Deposit Plan consultation stage to highlight sewerage and water infrastructure requirements associated with proposed sites. The appendix will need to accurately reflect our representations and recognise that the demands on our infrastructure changes over time, and the capacity of existing infrastructure to accommodate the proposed allocations may change over the course of the LDP period. Notwithstanding this information, we have made comments on specific sites below:
• PrC1/MU2 Pibwrlwyd Hydraulic Modelling Assessment (HMA) of the water supply network will be required.
• PrC3/MU1 Emlyn Brickworks Hydraulic Modelling Assessment (HMA) of the water supply network will be required.
• SeC16/MU1 Beechwood, Llandeilo Reinforcements will be required at Ffairfach Wasterwater Treatment Works (WwTW).
• PrC1/MU3 Nant y Caws There are no public sewers nearby therefore the provisions of WG Circular 008/2018 “Planning requirements in respect of the use of private sewerage in new development, incorporating septic tanks and small sewage treatment plants” apply.
Noted.
The Council considers that the 4 sites highlighted within the representation can be updated to reflect the most up to date information.